Lot#2 : Procurement of construction/Installation work of MV/LV Network

Financials
Total Budget Spent
$1,609,134 $1,386,533
FY Budget Spent
$1,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Herat
Funding Agency World Bank
Exp/Start Date 14-May-19
Contractual Completion Date 13-Feb-20
Expected Completion Date 13-Feb-20
Lot#2 : Procurement of construction/Installation work of MV/LV Network
Project Description: Construction and erection of 20/0.4kV Distribution Networks in Chesht Sharif and Hobai districts of Herat Province
Donor: 3
Start Date: 2019-05-14
End Date: 2020-02-13
Location: Herat
Physical Progress: 99.00%
Financial Progress: 14.92%
Progress Status: ongoing
Expected Results: To provide electricity to households, institutions, and businesses in the Chesht and Hobai districts of Herat Province, Afghanistan