Lot#1: Procurement of works and Installation Services for MV/LV Distribution Networks (Karokh and Pashtun Zarghoon)

Financials
Total Budget Spent
$1,079,457 $607,149
FY Budget Spent
$800,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Herat
Funding Agency World Bank
Exp/Start Date 11-May-19
Contractual Completion Date 31-Aug-20
Expected Completion Date 10-Feb-20
Lot#1: Procurement of works and Installation Services for MV/LV Distribution Networks (Karokh and Pashtun Zarghoon)
Project Description: Construction and erection of 20/0.4kV Distribution Networks in Karokh and Pashtun Zarghoon districts of Herat Province
Donor: 3
Start Date: 2019-05-11
End Date: 2020-02-10
Location: Herat
Physical Progress: 100.00%
Financial Progress: 9.70%
Progress Status: ongoing
Expected Results: To provide electricity to households, institutions, and businesses in the Karokh and Pashtun Zarghon Districts of Herat Province, Afghanistan
  Back