Lot 2 Implementation of CASA-1000 Transmission Line

Financials
Total Budget Spent
$88,261,376 $53,311,383
FY Budget Spent
$8,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Multi-Provinces
Funding Agency World Bank
Exp/Start Date 25-Jun-19
Contractual Completion Date 24-Jun-22
Expected Completion Date 24-Jun-22
Lot 2 Implementation of CASA-1000 Transmission Line
Project Description: Design Supply construction testing and commissioning of 500 KV HVDC Transmission Line from Dehsala District of Baghlan Province upto Gulbahar of Kapisa Province.
Donor: 3
Start Date: 2019-06-25
End Date: 2022-06-24
Location: Multi-Provinces
Physical Progress: 64.11%
Financial Progress: 53.64%
Progress Status: ongoing
Expected Results: Transmission of 1300 MW electricity from Central Asia to South Asia.