Consultancy Services for ESIA

Financials
Total Budget Spent
$649,993 $107,539
FY Budget Spent
$140,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency World Bank
Exp/Start Date 19-Apr-19
Contractual Completion Date 19-Oct-21
Expected Completion Date 19-Oct-21
Consultancy Services for ESIA
Project Description: consultancy services for environmental and social impact assessment of Naghlu hydropower plant.
Donor: 3
Start Date: 2019-04-19
End Date: 2021-10-19
Location: Kabul
Physical Progress: 10.00%
Financial Progress: 18.19%
Progress Status: ongoing
Expected Results: Naghlu hydropower plant safety impact on the environment and society.