220/20 kV Substation at Arghandi

Financials
Total Budget Spent
$19,987,256 $18,279,542
FY Budget Spent
$1 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency Asian Development Bank (ADB)
Exp/Start Date 28-Jun-16
Contractual Completion Date 15-Jan-19
Expected Completion Date 18-Jun-18
220/20 kV Substation at Arghandi
Project Description: Procurment of plant, design, supply, installation, testing and commissioning of kabul south west 220/20 kv substation (Arghand)
Donor: 5
Start Date: 2016-06-28
End Date: 2018-06-18
Location: Kabul
Physical Progress: 100.00%
Financial Progress: 85.93%
Progress Status: ongoing
Expected Results: The scope of work for Kabul South West 220/20 kV Arghandi substation includes the Design, manufacture, test, deliver, install and commissioning works