Supply, Construction and Commissioning of 220kV Salang Tunnel Substation and 20kV Network

Financials
Total Budget Spent
$20,369,720 $15,914,271
FY Budget Spent
$2,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Parwan
Funding Agency USAID
Exp/Start Date 18-Apr-17
Contractual Completion Date 01-Apr-20
Expected Completion Date 18-Sep-19
Supply, Construction and Commissioning of 220kV Salang Tunnel Substation and 20kV Network
Project Description: Supply, Construction, and Commissioning of 220 kV Salang Tunnel Substation and 20kV Network was signed with Usluel-Omran JV company on September 28, 2016. The substation is planned to be constructed in Parwan province, Salang district and it will electrify the Salang Tunnel and a small distribution grid. the Salang Substation will have two step down transformers with rating of 4MVA, 220/20kV each and five Auxiliary distribution transformers with rating of 20kV/400V each. the project started on April 18th, 2017.
Donor: 6
Start Date: 2017-04-18
End Date: 2019-09-18
Location: Parwan
Physical Progress: 99.62%
Financial Progress: 78.13%
Progress Status: ongoing
Expected Results: Based on the scope of work for this project, a High Voltage 220kV Substation for Salang Tunnel will be constructed along with a 20kV Network near the South Entrance of the Salang Tunnel, at Gowarah Sang, Afghanistan. This project will include a new substation for the Tunnel, residence building, and medium voltage (MV) distribution system.