Rehabilitation of Gereshk HPP

Financials
Total Budget Spent
$38,316,542 $31,106,971
FY Budget Spent
$2,693,244 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Helmand
Funding Agency Asian Development Bank (ADB)
Exp/Start Date 10-Oct-12
Contractual Completion Date 22-Nov-20
Expected Completion Date 10-Oct-14
Rehabilitation of Gereshk HPP
Project Description: Brief Information: Gereshk Electricity Services Improvement Program Project 3 - Under ADB was signed on 6th February 2012. The Project is located in Gereshk town of Helmond Province. ICB No.: ICB-DABS/Gereshk HPP 012/2010. The Project shall have enhanced Electricity Services while replacing 3.3/0.4 kV System to 20 kV/ 0.4 kV Line and Distribution System.
Donor: 5
Start Date: 2012-10-10
End Date: 2014-10-10
Location: Helmand
Physical Progress: 100.00%
Financial Progress: 81.18%
Progress Status: ongoing
Expected Results: Main Objective of the Project is to enhance the Generating Capacity of the Plant and Renovate the Old Turbines and Install a new Turbine. Total enhanced capacity of the Project after the Commissioning shall be 4.8MW. Also, new 20/0.4 kV Distribution system will enhance the quality of Electricity supplies in Gereshk and adjoining villages.