Ozbin Distribution Network

Financials
Total Budget Spent
$0 $0
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency DABS
Exp/Start Date 25-Jul-15
Contractual Completion Date 01-Jun-21
Expected Completion Date 14-Jun-21
Ozbin Distribution Network
Project Description: The 20/0.4 kV Distribution Network of Ozbine area, Sarawbi District Kabul province, and Implementation of this project is the responsibility of Kabul Breshna . The capacity of the project is 10.02 MWA which includes 51 transformers.
Donor: 8
Start Date: 2015-07-25
End Date: 2021-06-14
Location: Kabul
Physical Progress: 83.00%
Financial Progress: 0.00%
Progress Status: ongoing
Expected Results: After completion of this project, 8000 Homes will use electrical energy.
  Back