Lot #2 – Design, Supply, Construction, Erection, Testing and Commissioning of 110kV S/C tapping transmission line from Salma (Hydel) to Karokh Substation

Financials
Total Budget Spent
$5,466,896 $4,143,261
FY Budget Spent
$1,400,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Herat
Funding Agency World Bank
Exp/Start Date 15-Jan-18
Contractual Completion Date 18-May-20
Expected Completion Date 15-Jul-19
Lot #2 – Design, Supply, Construction, Erection, Testing and Commissioning of 110kV S/C tapping transmission line from Salma (Hydel) to Karokh Substation
Project Description: This project include Design, Supply, Installation, Testing and commissioning of 110Kv transmission line. This line will be tapped from existing Salma-Noreljehad 110kv Transmission line to the new Karrokh 110/20 kv Substation.
Donor: 3
Start Date: 2018-01-15
End Date: 2019-07-15
Location: Herat
Physical Progress: 100.00%
Financial Progress: 75.79%
Progress Status: ongoing
Expected Results: The main objectives of this project is to build 110kv tapping transmission line to be tapped from existing 110kv Transmission line between Salma dam and Nor-e-aljehad Substation and energize 110/20kv Karrokh Substation.