220 kV D/C OHL from Doshi to Bamyan

Financials
Total Budget Spent
$43,861,624 $27,467,898
FY Budget Spent
$15,603,839 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Multi-Provinces
Funding Agency Asian Development Bank (ADB)
Exp/Start Date 04-Dec-18
Contractual Completion Date 28-Nov-21
Expected Completion Date 21-Dec-20
220 kV D/C OHL from Doshi to Bamyan
Project Description: Procurement of Plant Design, Supply, Installation, Testing, and Commissioning of 220kV double circuits transmission line which carries 300 MV energy from Doshi substation to Bmayan substation.
Donor: 5
Start Date: 2018-12-04
End Date: 2020-12-21
Location: Multi-Provinces
Physical Progress: 76.00%
Financial Progress: 62.62%
Progress Status: ongoing
Expected Results: By implementation of this project, 300 MW of energy will be transferred to Bamyan Substatation and will be distributed to 20,000 consumers in Bamyan city.