500KV Transmission line from Dasht-e-Alwan to Arghandi

Financials
Total Budget Spent
$173,130,536 $150,106,930
FY Budget Spent
$9,388,829 $22,826,110
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Multi-Provinces
Funding Agency Asian Development Bank (ADB)
Exp/Start Date 06-Oct-16
Contractual Completion Date 30-Jun-21
Expected Completion Date 05-Oct-19
500KV Transmission line from Dasht-e-Alwan to Arghandi
Project Description: this project is a part of North-south Power Transmission enhancement project, contract awarded on 7.06.2016 to M/S KPTL for procurement of plant, design, supply, installation, testing, commissioning of 500 KV D/C Transmission line from Dasht-e-alwan to Arghande. With contract number DABS/015/ICB package 8. The proposed line estimated length of 238.545 KM traverses salang hilly terrain following the main road A76 and parallel to existing 220 KV line.
Donor: 5
Start Date: 2016-10-06
End Date: 2019-10-05
Location: Multi-Provinces
Physical Progress: 89.00%
Financial Progress: 86.70%
Progress Status: ongoing
Expected Results: The main objectives of the project are enhancement in the capacity of Electricity in afghanistan, this project will solve the elecric problem in kabul or south provinces.The distribution project scope includes Procurement of Plant, design, supply and installation of 500 Kv D/C transmission line from dasht-e-Alwan to Arghande and Procurement of Plant, design, supply and installation of LOOP in dasht-e-Alwan 500/220 KV substation of double circuit 220 KV