ANA AEI 1/203 Brigade Garrison Camp Calrck (USACE)

Financials
Total Budget Spent
$4,561,532 $0
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Khost
Funding Agency USAID
Exp/Start Date 29-Sep-19
Contractual Completion Date
Expected Completion Date 03-Jul-21
ANA AEI 1/203 Brigade Garrison Camp Calrck (USACE)
Project Description:
Donor: 6
Start Date: 2019-09-29
End Date: 2021-07-03
Location: Khost
Physical Progress: 0.00%
Financial Progress: 0.00%
Progress Status: ongoing
Expected Results:
  Back