Ministry of Defense Headquarters Base connection (USACE)

Financials
Total Budget Spent
$2,244,574 $0
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency USAID
Exp/Start Date 01-Aug-19
Contractual Completion Date
Expected Completion Date 01-Aug-21
Ministry of Defense Headquarters Base connection (USACE)
Project Description: Construction of a medium voltage distribution line from Breshna kot substation of MoD HQ
Donor: 6
Start Date: 2019-08-01
End Date: 2021-08-01
Location: Kabul
Physical Progress: 0.00%
Financial Progress: 0.00%
Progress Status: ongoing
Expected Results: Electrification of the new facilities built by USACE inside MoD HQ
  Back