Construction of Faizabad HEPP

Financials
Total Budget Spent
$18,856,428 $42,087,175
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Badakhshan
Funding Agency Government of Afghanistan
Exp/Start Date 17-Sep-14
Contractual Completion Date 09-Jan-18
Expected Completion Date 16-Sep-16
Construction of Faizabad HEPP
Project Description: Faizabad HEPP is a small dam and run of river hyderopower scheme with 3 number of Kaplan Turbines whose total capacity is 7.5MW. The project is funded by KfW whose contractor is Feka and the Consultant company is Fichtner.
Donor: 7
Start Date: 2014-09-17
End Date: 2016-09-16
Location: Badakhshan
Physical Progress: 96.60%
Financial Progress: 102.15%
Progress Status: ongoing
Expected Results: The project total capacity is 7.5 MW that will produce electricity for approx. 15,000 households.