Lot 9 Extension at Mazar-e- Sharif Substation

Financials
Total Budget Spent
$4,594,268 $2,331,160
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Balkh
Funding Agency Government of Afghanistan
Exp/Start Date 04-Sep-19
Contractual Completion Date 09-Feb-22
Expected Completion Date 21-Nov-21
Lot 9 Extension at Mazar-e- Sharif Substation
Project Description: Lot 9: Amendment No.1-Transformer extension at Mazar-e-Sharif Substation: ●Supply and Installation of an additional transformer bay for the accommodation of the repaired transformer; ●Dismantling of existing 50 MVA transformer and all the shipments to/from abroad for repairing; ●Installation of all additional electrical and civil structures and equipment for accommodation of repaired transformer; ●Supply and Installation of 20kV Panels and cables between the 220/20kV transformer and the 20kV Switchgear; ● All civil and structural works, foundations, cable trenches/troughs etc. as required for new 50 MVA Tr.
Donor: 7
Start Date: 2019-09-04
End Date: 2021-11-21
Location: Balkh
Physical Progress: 59.00%
Financial Progress: 61.86%
Progress Status: ongoing
Expected Results: Lot 9: Amendment No.1-Transformer extension at Mazar-e-Sharif Substation: ●Supply and Installation of an additional transformer bay for the accommodation of the repaired transformer; ●Dismantling of existing 50 MVA transformer and all the shipments to/from abroad for repairing; ●Installation of all additional electrical and civil structures and equipment for accommodation of repaired transformer; ●Supply and Installation of 20kV Panels and cables between the 220/20kV transformer and the 20kV Switchgear; ● All civil and structural works, foundations, cable trenches/troughs etc. as required for new 50 MVA Tr.