Design, Supply and Installation of 5.5 MW Hybrid Solar PV Power Plant at Dykondi Province

Financials
Total Budget Spent
$13,070,397 $181,116
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Daikundi
Funding Agency Government of Afghanistan
Exp/Start Date 05-Aug-18
Contractual Completion Date 02-Oct-20
Expected Completion Date 03-Feb-20
Design, Supply and Installation of 5.5 MW Hybrid Solar PV Power Plant at Dykondi Province
Project Description: Daykundi Hybrid solar PV Power plant consists of seven sites in Nilli center of province and in three districts . Total energy output of the project is 5.5MW Solar AC, 3.4MW load battery backup for 4 hours and total of 4.3MW Disel backup system to be integrated.
Donor: 7
Start Date: 2018-08-05
End Date: 2020-02-03
Location: Daikundi
Physical Progress: 2.00%
Financial Progress: 1.39%
Progress Status: ongoing
Expected Results: Implementation of this project will provide job opportunities for the Local residents in the six sites and Nilli City as well as provide electricity facility to around 10000 customers of the aimed sites.