Procurement of Design, Supply, Construction, Erection, Testing and Commissioning of 110/20kV Sarobi Substation

Financials
Total Budget Spent
$3,573,847 $2,879,876
FY Budget Spent
$1,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency World Bank
Exp/Start Date 28-Mar-17
Contractual Completion Date 24-Mar-19
Expected Completion Date 28-Jun-18
Procurement of Design, Supply, Construction, Erection, Testing and Commissioning of 110/20kV Sarobi Substation
Project Description: Sarobi 110/20 kV Substation is a distrubtion substation supplying 20 kV feeders to Sarobi and Tagab new Villages around Naghlu Dam, the substation capacity is 2x20MVA which is currently one transformer is installed, and another is in future plan of DABS.
Donor: 3
Start Date: 2017-03-28
End Date: 2018-06-28
Location: Kabul
Physical Progress: 100.00%
Financial Progress: 80.58%
Progress Status: ongoing
Expected Results: This substation will upgrade the previous old network of Sarobi from 6kv to 20 kV ,that will decrease the loses of electricity, and as well, with the completion of this project more than 17 new villages in Sarobi district and some close villages of Tagab will also be electrified form this substation. Totally we can supply electricity around 20,000 households through this substation.