Design and Build of Mana Gai 2.1 MW Small Hydropower Project in Kunar Province

Financials
Total Budget Spent
$9,885,798 $9,130,041
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kunnar
Funding Agency Government of Afghanistan
Exp/Start Date 18-Feb-13
Contractual Completion Date 14-Mar-18
Expected Completion Date 17-Feb-18
Design and Build of Mana Gai 2.1 MW Small Hydropower Project in Kunar Province
Project Description: Design and Build of 2.1 MW Small Hydropower Plant Project on Pech river of Manogai District of Kunar Province. The project consists of two units of Francis turbines and gensets and by completion of the project, total 4000 customers will be electrified.
Donor: 7
Start Date: 2013-02-18
End Date: 2018-02-17
Location: Kunnar
Physical Progress: 98.00%
Financial Progress: 92.36%
Progress Status: ongoing
Expected Results: Hydropower generation for electrification of 4000 customers in Manogai, Wattapur, Chaghan Districts and Asad Abad in Kunar Province. Creating job apportunities for approximately 270 individuals and socio-economic development of the region.