Survey-Design and build of 600 KW Micro Hydropower Project in Charkh-Logar

Financials
Total Budget Spent
$121,084 $807,660
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Logar
Funding Agency Government of Afghanistan
Exp/Start Date 19-May-14
Contractual Completion Date 30-Jul-22
Expected Completion Date 19-Mar-17
Survey-Design and build of 600 KW Micro Hydropower Project in Charkh-Logar
Project Description: This project is located at Charkh district of Logar province and contracted with Balt Hydro Building Russian company, it has been progressed 46 % physically and 14.5% financially so far. Right now the project woks has been stopped due to contract time expiration.
Donor: 7
Start Date: 2014-05-19
End Date: 2017-03-19
Location: Logar
Physical Progress: 46.00%
Financial Progress: 24.85%
Progress Status: ongoing
Expected Results: With the completion of the project 1340 household would be use the energy for the illumination of their houses. It would bring positive change in economic and cultural life of the people of the people of the project site.