Rehabilitation, Design, Supply, Installation, Distribution, & Operation of Micro Hydro Electric Power Plant Project in Chack District, Wardak Province

Financials
Total Budget Spent
$12,437,632 $6,933,573
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Wardak
Funding Agency Government of Afghanistan
Exp/Start Date 01-Aug-16
Contractual Completion Date
Expected Completion Date 09-Oct-19
Rehabilitation, Design, Supply, Installation, Distribution, & Operation of Micro Hydro Electric Power Plant Project in Chack District, Wardak Province
Project Description: Funded by : GoIRA 925,359,836.05 AFN Project Budget Beneficiaries: 4000 Family Contract Signing Date:01-Aug-2016 Contract Duration:36 Months Contract End Date: 09-Oct-2019 Extended Duration: 9.5 months Revised Completion Date: 23-Jul-2020 Expected Completion Date: 30-Dec-2021 Contractor: AHCC & UJRCC JV Project physical progress (%) 54.42 % Project Financial progress (%): 45.58 %
Donor: 7
Start Date: 2016-08-01
End Date: 2019-10-09
Location: Wardak
Physical Progress: 55.00%
Financial Progress: 55.75%
Progress Status: ongoing
Expected Results: Micro Hydro Electric Power Plant Project in Chack District, Wardak Province, the objective is to bring reliable and sustainable electric power to Chak Wardak 4000 Household. The availability of reliable power enables hospitals, schools and businesses to remain open longer, improves the quality of life for the Afghan people, and helps attract investment in new industrial and commercial enterprises. This helps create new job opportunities and economic growth for the war-torn region.