Supply and Installation of 20/0.4 KV Distribution of Sorkh Road District of Jalalabad Province

Financials
Total Budget Spent
$1,090,639 $857,776
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Nangarhar
Funding Agency Government of Afghanistan
Exp/Start Date 08-Jan-18
Contractual Completion Date 22-Nov-19
Expected Completion Date 09-Jan-19
Supply and Installation of 20/0.4 KV Distribution of Sorkh Road District of Jalalabad Province
Project Description: The Project includes 10 Nos. distribution Transformers along with all necessary equipment’s/ Materials such as MV/LV Concrete Poles, MV Conductors, LV AB Cables, Meter Boxes ,LVDB and etc.
Donor: 7
Start Date: 2018-01-08
End Date: 2019-01-09
Location: Nangarhar
Physical Progress: 96.00%
Financial Progress: 78.65%
Progress Status: ongoing
Expected Results: Electrification of about 3400 Households and social development economy.