Supply and Installation of Extension of Distribution for Jalalabad Province , Afghanistan ( Phase II)

Financials
Total Budget Spent
$374,581 $143,515
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Nangarhar
Funding Agency Government of Afghanistan
Exp/Start Date 22-Jul-17
Contractual Completion Date 22-Jul-18
Expected Completion Date 22-Jul-18
Supply and Installation of Extension of Distribution for Jalalabad Province , Afghanistan ( Phase II)
Project Description: The Project includes 4 Nos. distribution Transformers along with all necessary equipment’s/ Materials such as MV/LV Concrete Poles, MV Conductors, LV AB Cables, Meter Boxes ,LVDB and etc.
Donor: 7
Start Date: 2017-07-22
End Date: 2018-07-22
Location: Nangarhar
Physical Progress: 100.00%
Financial Progress: 38.31%
Progress Status: ongoing
Expected Results: Electrification of about 800 Housholds and social development economy .