4MW Micro hydropower project of Parranda Punjshir Province

Financials
Total Budget Spent
$7,640,975 $6,490,469
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Panjsher
Funding Agency Government of Afghanistan
Exp/Start Date 21-Apr-13
Contractual Completion Date 26-Dec-20
Expected Completion Date 12-Nov-14
4MW Micro hydropower project of Parranda Punjshir Province
Project Description: The total physical work of the project has been completed by about 96%, and the Financial percentage is about 79%.Production of Turbines, generators and control systems) have been started in Czech and Bulgarian companies, which will be ready to transfer to Afghanistan after completing the testing process. Note: If no serious problems are revealed in the equipment transfer process, it is expected that the project will be completed within a certain period (December 26, 2020).
Donor: 7
Start Date: 2013-04-21
End Date: 2014-11-12
Location: Panjsher
Physical Progress: 96.00%
Financial Progress: 102.93%
Progress Status: ongoing
Expected Results: This project shall produce electricity for 7500 families and has a very positive effect on the development of the people's economy and raises the standard of living of the people and provides the ground for people to have access to today's technology.