220/20 kV Substation in Bamyan and Expansion of 220/kV Doshi Substation

Financials
Total Budget Spent
$11,694,974 $4,945,383
FY Budget Spent
$6,850,832 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Bamyan
Funding Agency Asian Development Bank (ADB)
Exp/Start Date 11-Jan-19
Contractual Completion Date 31-Oct-21
Expected Completion Date 30-Dec-20
220/20 kV Substation in Bamyan and Expansion of 220/kV Doshi Substation
Project Description: Bamyan substation Project was awarded to XEPC on the March 2018. This project located in Bamyan province. The project consists of a 220/20 Kv substation, and extension of work at 220/20 Kv Doshi Substation. The substations will feed 20 Kv Bamyan network. The 220 kV outdoor switchyard shall have a double busbar arrangement and include 2(two) line bays, 2(two) transformer bays, 1 (one) bus coupler bay, and busbar voltage measuring at each busbar. In order to allow for future extension the busbars. the Contract document Has been signed on 22-April-2018, Advance payment Guarantee has been submitted on 13-06-2018, and advance payment has been given to XEPC, the project Kickoff meeting with contractor was held on 02-07-2018 and discussed on important issue off contract.
Donor: 5
Start Date: 2019-01-11
End Date: 2020-12-30
Location: Bamyan
Physical Progress: 68.00%
Financial Progress: 42.07%
Progress Status: ongoing
Expected Results: The main objectives of the project are enhancement in the capacity of Substation System by adding a new substation at Azhdar valley of Bamyan.The substation project scope includes survey, design, supply, installation and commissioning of plant in Substation of Bamyan And extension of Doshi Substation . The susbstation will support a total number of estimated beneficiaries in 20000 residential consumers respectively.