Owner's Engineer, CASA-1000

Financials
Total Budget Spent
$2,001,400 $938,809
FY Budget Spent
$1,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Multi-Provinces
Funding Agency World Bank
Exp/Start Date 20-Oct-18
Contractual Completion Date 19-Sep-18
Expected Completion Date 19-Sep-22
Owner's Engineer, CASA-1000
Project Description: Consulting Services for the Design and Implementation of CASA-1000 Project
Donor: 3
Start Date: 2018-10-20
End Date: 2022-09-19
Location: Multi-Provinces
Physical Progress: 60.00%
Financial Progress: 46.91%
Progress Status: ongoing
Expected Results: Supervision and Implementation of the 570 kM of CASA-1000 OHL