Curriculum development for DABS training Center

Financials
Total Budget Spent
$107,390 $63,628
FY Budget Spent
$107,390 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status completed
Location Kabul
Funding Agency World Bank
Exp/Start Date 01-Apr-19
Contractual Completion Date 31-Jul-20
Expected Completion Date 01-Feb-20
Curriculum development for DABS training Center
Project Description: This company will devolve the curriculum to DABS training center .
Donor: 3
Start Date: 2019-04-01
End Date: 2020-02-01
Location: Kabul
Physical Progress: 100.00%
Financial Progress: 55.90%
Progress Status: completed
Expected Results: The DABS new staff will be trained and will use from this curriculum to improve his capacity building.