NEPS/SEPS Connector Five Transmission Lines from Ghazni to Kandahar East in One Lot

Financials
Total Budget Spent
$129,233,455 $97,084,819
FY Budget Spent
$20,000,000 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Multi-Provinces
Funding Agency USAID
Exp/Start Date 01-Aug-17
Contractual Completion Date 31-Dec-20
Expected Completion Date 31-Dec-19
NEPS/SEPS Connector Five Transmission Lines from Ghazni to Kandahar East in One Lot
Project Description: Design, Construct, Test, Deliver and Commission fully functional double circuit, duplex conductor per phase, 220kV Transmission Line segments starting at existing Ghazni Substation and ending at Kandahar East Substation.
Donor: 6
Start Date: 2017-08-01
End Date: 2019-12-31
Location: Multi-Provinces
Physical Progress: 86.00%
Financial Progress: 75.12%
Progress Status: ongoing
Expected Results: Ghazni-Kandahar 220KV D/C Transmission Line was signed with KEC international company on the 26/February/2017 . This Transmission Line project located in Ghazni, Zabul and Kandahar provinces which has multi purposes. 1- Connection NEPS to SEPS power grids. 2- New medium and high voltage transmission lines to expand NEPS and connect NEPS with SEPS. 3- Improvements to Agriculture. 4- Increased industrial Activities. 5- Cheaper electricity to residential of Ghazni, Zabul and Kandahar.