Procurement of Works for Warehouses Construction

Financials
Total Budget Spent
$145,345 $140,476
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency World Bank
Exp/Start Date 29-Jun-15
Contractual Completion Date 30-Apr-16
Expected Completion Date 15-Dec-15
Procurement of Works for Warehouses Construction
Project Description: the project consist of two lots, 1- construction of two small warehouses and renovation of old warehouse 2- design, supply, and construction of one big warehouse.
Donor: 3
Start Date: 2015-06-29
End Date: 2015-12-15
Location: Kabul
Physical Progress: 100.00%
Financial Progress: 96.65%
Progress Status: ongoing
Expected Results: construction of warehouses will grant a safe environment to keep the power plant spare parts in good condition for operation and maintenance of the power plant.