Work contract for rehabilitation of Unit #1 and overhauling of Unit #3 at NHPS

Financials
Total Budget Spent
$6,600,000 $10,245,816
FY Budget Spent
$1,343,244 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status ongoing
Location Kabul
Funding Agency World Bank
Exp/Start Date 24-Aug-16
Contractual Completion Date 30-Oct-18
Expected Completion Date 22-May-17
Work contract for rehabilitation of Unit #1 and overhauling of Unit #3 at NHPS
Project Description: Work contract for rehabilitation of Unit #1 and overhauling of Unit #3 at NHPS
Donor: 3
Start Date: 2016-08-24
End Date: 2017-05-22
Location: Kabul
Physical Progress: 100.00%
Financial Progress: 96.38%
Progress Status: ongoing
Expected Results: Work contract for rehabilitation of Unit #1 and overhauling of Unit #3 at NHPS, to bring both units (1&3) to the operation.