Bayat Power IPP

Financials
Total Budget Spent
$38,850,000 $0
FY Budget Spent
$0 $0
 
Progress
Major Milestones
Overall Planned
Overall Actual
Overview
Current Status completed
Location Jawzjan
Funding Agency Government of Afghanistan
Exp/Start Date 01-Apr-18
Contractual Completion Date 09-Nov-19
Expected Completion Date 29-Jan-19
Bayat Power IPP
Project Description: this is a thermal Power plant which is contracted as Power Purchase agreement (PPA) between DABS and Bayat IPP(independent Power Plant), located in Jawzjan and it is aim to produce 40 MW from gas to Jawzjan, Faryab and Mazar
Donor: 7
Start Date: 2018-04-01
End Date: 2019-01-29
Location: Jawzjan
Physical Progress: 100.00%
Financial Progress: 0.00%
Progress Status: completed
Expected Results: This Thermal plant will increase the internal power production of Jawzjan, Faryab and Mazar about 40MW